
Building Project Updates
We are currently in the process of adding onto and renovating our building!
Please pardon our mess!
Please pardon our mess!
Completed
Roadmap
- Stage cavity opened up.
- Ceiling painted.
- Walls painted.
- Drywall completed.
- New stage started.
- Drywall started in Worship Center.
- Gym bathrooms completed.
- New downspout and wider gutters installed on south side.
- Parking lot paved and striped.
- Storm sewer line and catch basins installed by the town.
- Fire doors installed between Worship Center and Gym.
- Siding and stone accents added to south side bump-out.
- Air conditioning units for Worship Center installed.
- Northeast corner door on Gym replaced.
- Floor, roof, and walls constructed for south side bump-out.
- Steel beam for south side bump-out is installed.
- Foyer doors were replaced in March.
- The Gym is in good shape.
- Bathrooms and walk-through hallway remain to be completed.
- The trees have been removed on the north side. Tree stumps to be moved from property. Parking lot drain area completed and available for use.
- Parking lot black topping being investigated to be included in 2025.
- Phase 2 North Bump-out drawings are in process.
- Phase 2 Target Start: 2025
Current Work:
Future Work:
- Finish up the Fire Wall in the Storage Area.
- Continue working on the wiring for the Stage area and place the plywood down when electrical is completed.
- Finish off the Wall Painting and maybe the ceiling as well (additional coats).
- Continue to work on Sound Boards.
- Place Nailing Blocks up
- Build framework
- Install Dacron and insulation
- Build Burlap Caps Frames
- Work on hanging new lights. Test dimming/diffusing.
Future Work:
- Stage area:
- Electrical and sound feeds
- Plywood down
- Front 3' extension
- Electric run for ceiling
- Ceiling drywall
- Frame in closets
- Drywall closets
- Begin to build large overhang soffit
- Storage Room:
- Complete Firewall
- Build ramp and landing
- Order fire door for stage
- Paint :
- Remainder of ceiling - Will do touch up as needed
- Pillars:
- Frame in
- Soffit:
- Frame in
- Ceiling:
- Work on supports for the Speaker moves
- Doors:
- Order the New Doors that are needed
- North Bump Out:
- WORK TO BEGIN EARLY MAY
- Remove Siding
- Remove Brick