![](https://storage2.snappages.site/RD7D3K/assets/images/6457401_1920x1080_500.jpg)
Building Project Updates
We are currently in the process of adding onto and renovating our building!
Please pardon our mess!
Please pardon our mess!
Recent Updates
- Fire doors installed between Worship Center and Gym.
- Siding and stone accents added to south side bump-out.
- Air conditioning units for Worship Center installed.
- Northeast corner door on Gym replaced.
- Floor, roof, and walls constructed for south side bump-out.
- Steel beam for south side bump-out is installed.
- Foyer doors were replaced in March.
- The Gym is in good shape.
- Bathrooms and walk-through hallway remain to be completed.
- The trees have been removed on the north side. Tree stumps to be moved from property. Parking lot drain area completed and available for use.
- Parking lot black topping being investigated to be included in 2025.
- Phase 2 North Bump-out drawings are in process.
- Phase 2 Target Start: 2025