
Building Project Updates
We are currently in the process of adding onto and renovating our building!
Please pardon our mess!
Please pardon our mess!
GBC Building Update - 10/21/25
 New Foyer Work to be Completed
Wiring for Lighting — GBC
Insulation —
Gutters — Contractor — 10/30
Breaker Box install — GBC - by 10/31
Drywall delivery — H.B.M. - 10/24
Drywall install — date TBD
Mudding/Sanding —(Contractor, Rickie) date TBD
Painting — in-house GBC - date TBD
Emergency lights/signs — GBC date TBD
Foyer doors installed — GBC — arrival 12/1
Trim work — GBC date TBD
Grind down concrete floor in foyer (polished floor) GBC date TBD
Completed:
Remaining Work in Worship Center - All Dates TBD
Wiring for Lighting — GBC
- Recessed lights (84)
 - Chandeliers (4)
 - Exterior Lighting (9)
 
Insulation —
- Wall insulation (GBC) — 80% complete
 - Ceiling — Contractor providing estimate
 
Gutters — Contractor — 10/30
Breaker Box install — GBC - by 10/31
- Rough inspection
 
Drywall delivery — H.B.M. - 10/24
Drywall install — date TBD
Mudding/Sanding —(Contractor, Rickie) date TBD
Painting — in-house GBC - date TBD
Emergency lights/signs — GBC date TBD
Foyer doors installed — GBC — arrival 12/1
Trim work — GBC date TBD
Grind down concrete floor in foyer (polished floor) GBC date TBD
Completed:
- Chair cleaning
 - Concrete around porch (foyer)
 - Water drains — gutters
 - Blacktop binder — north side
 
Remaining Work in Worship Center - All Dates TBD
- New door installs
 - Kitchen / storage room / stage door (fire) / youth door
 - Double Door (east entrance from hallway to worship center)
 - Ceiling fan installs (2)
 - Install soffit outlets
 - Baseboard trim install
 - Sound booth install
 - Exit lights install
 - Smoke detectors & horns install
 - Run conduit and wire for choir mics
 - Install shrouds around lights
 - Look into installing spotlights for stage area
 - Paint pulpit
 - Repair floor area near stage stairs
 
Previously Completed
- Canopy above the stage completed.
 - New stage mostly completed.
 - Trusses and roof added to new foyer.
 - Overhead lights installed in stage ceiling.
 - Stage drywall completed.
 - Construction on new foyer begun.
 - Plywood added to stage.
 - Siding and brick removed from north exterior wall.
 - New lights installed and diffusers added.
 - Sound boards mostly complete (waiting to move temporary stage).
 - Pillars mostly completed (waiting to move temporary stage).
 - Wall & ceiling painting completed.
 - Stage cavity opened up.
 - Ceiling painted.
 - Walls painted.
 - Drywall completed.
 - New stage started.
 - Drywall started in Worship Center.
 - Gym bathrooms completed.
 - New downspout and wider gutters installed on south side.
 - Parking lot paved and striped.
 - Storm sewer line and catch basins installed by the town.
 - Fire doors installed between Worship Center and Gym.
 - Siding and stone accents added to south side bump-out.
 - Air conditioning units for Worship Center installed.
 - Northeast corner door on Gym replaced.
 - Floor, roof, and walls constructed for south side bump-out.
 - Steel beam for south side bump-out is installed.
 - Foyer doors were replaced in March.
 - The Gym is in good shape.  
- Bathrooms and walk-through hallway remain to be completed.
 
 - The trees have been removed on the north side. Tree stumps to be moved from property. Parking lot drain area completed and available for use.
 - Parking lot black topping being investigated to be included in 2025.
 - Phase 2 North Bump-out drawings are in process.
 - Phase 2 Target Start: 2025
 
