
Building Project Updates
We are currently in the process of adding onto and renovating our building!
Please pardon our mess!
Please pardon our mess!
GBC Building Update - 10/21/25
New Foyer Work to be Completed
Wiring for Lighting — GBC
Insulation —
Gutters — Contractor — 10/30
Breaker Box install — GBC - by 10/31
Drywall delivery — H.B.M. - 10/24
Drywall install — date TBD
Mudding/Sanding —(Contractor, Rickie) date TBD
Painting — in-house GBC - date TBD
Emergency lights/signs — GBC date TBD
Foyer doors installed — GBC — arrival 12/1
Trim work — GBC date TBD
Grind down concrete floor in foyer (polished floor) GBC date TBD
Completed:
Remaining Work in Worship Center - All Dates TBD
Wiring for Lighting — GBC
- Recessed lights (84)
- Chandeliers (4)
- Exterior Lighting (9)
Insulation —
- Wall insulation (GBC) — 80% complete
- Ceiling — Contractor providing estimate
Gutters — Contractor — 10/30
Breaker Box install — GBC - by 10/31
- Rough inspection
Drywall delivery — H.B.M. - 10/24
Drywall install — date TBD
Mudding/Sanding —(Contractor, Rickie) date TBD
Painting — in-house GBC - date TBD
Emergency lights/signs — GBC date TBD
Foyer doors installed — GBC — arrival 12/1
Trim work — GBC date TBD
Grind down concrete floor in foyer (polished floor) GBC date TBD
Completed:
- Chair cleaning
- Concrete around porch (foyer)
- Water drains — gutters
- Blacktop binder — north side
Remaining Work in Worship Center - All Dates TBD
- New door installs
- Kitchen / storage room / stage door (fire) / youth door
- Double Door (east entrance from hallway to worship center)
- Ceiling fan installs (2)
- Install soffit outlets
- Baseboard trim install
- Sound booth install
- Exit lights install
- Smoke detectors & horns install
- Run conduit and wire for choir mics
- Install shrouds around lights
- Look into installing spotlights for stage area
- Paint pulpit
- Repair floor area near stage stairs
Previously Completed
- Canopy above the stage completed.
- New stage mostly completed.
- Trusses and roof added to new foyer.
- Overhead lights installed in stage ceiling.
- Stage drywall completed.
- Construction on new foyer begun.
- Plywood added to stage.
- Siding and brick removed from north exterior wall.
- New lights installed and diffusers added.
- Sound boards mostly complete (waiting to move temporary stage).
- Pillars mostly completed (waiting to move temporary stage).
- Wall & ceiling painting completed.
- Stage cavity opened up.
- Ceiling painted.
- Walls painted.
- Drywall completed.
- New stage started.
- Drywall started in Worship Center.
- Gym bathrooms completed.
- New downspout and wider gutters installed on south side.
- Parking lot paved and striped.
- Storm sewer line and catch basins installed by the town.
- Fire doors installed between Worship Center and Gym.
- Siding and stone accents added to south side bump-out.
- Air conditioning units for Worship Center installed.
- Northeast corner door on Gym replaced.
- Floor, roof, and walls constructed for south side bump-out.
- Steel beam for south side bump-out is installed.
- Foyer doors were replaced in March.
- The Gym is in good shape.
- Bathrooms and walk-through hallway remain to be completed.
- The trees have been removed on the north side. Tree stumps to be moved from property. Parking lot drain area completed and available for use.
- Parking lot black topping being investigated to be included in 2025.
- Phase 2 North Bump-out drawings are in process.
- Phase 2 Target Start: 2025
