We are currently in the process of adding onto and renovating our building!
Please pardon our mess!
Please pardon our mess!
Recent Updates
- Foyer doors were replaced in March.
- The Gym is in good shape.
- Bathrooms and walk-through hallway remain to be completed.
- Northeast corner door section to be repaired/replaced (floor covering company is covering expense).
- The trees have been removed on the north side. Tree stumps to be moved from property. Parking lot drain area completed and available for use.
- Parking lot black topping being investigated to be included in 2025.
- Some work has been done in the Worship Center to prepare for the south bump-out, including footers poured for beam structure.
- Parco to start south side bump-out in May, 2024.
- Beam needs to be in place prior (April target).
- We are responsible for dry wall, stage, heating and electric.
- Phase 2 North Bump-out drawings are in process.
- Phase 2 Target Start: 2025