
Building Project Updates
We are currently in the process of adding onto and renovating our building!
Please pardon our mess!
Please pardon our mess!
Completed
Roadmap
- Trusses and roof added to new foyer.
- Overhead lights installed in stage ceiling.
- Stage drywall completed.
- Construction on new foyer begun.
- Plywood added to stage.
- Siding and brick removed from north exterior wall.
- New lights installed and diffusers added.
- Sound boards mostly complete (waiting to move temporary stage).
- Pillars mostly completed (waiting to move temporary stage).
- Wall & ceiling painting completed.
- Stage cavity opened up.
- Ceiling painted.
- Walls painted.
- Drywall completed.
- New stage started.
- Drywall started in Worship Center.
- Gym bathrooms completed.
- New downspout and wider gutters installed on south side.
- Parking lot paved and striped.
- Storm sewer line and catch basins installed by the town.
- Fire doors installed between Worship Center and Gym.
- Siding and stone accents added to south side bump-out.
- Air conditioning units for Worship Center installed.
- Northeast corner door on Gym replaced.
- Floor, roof, and walls constructed for south side bump-out.
- Steel beam for south side bump-out is installed.
- Foyer doors were replaced in March.
- The Gym is in good shape.
- Bathrooms and walk-through hallway remain to be completed.
- The trees have been removed on the north side. Tree stumps to be moved from property. Parking lot drain area completed and available for use.
- Parking lot black topping being investigated to be included in 2025.
- Phase 2 North Bump-out drawings are in process.
- Phase 2 Target Start: 2025
Current Work:
- Hang additional lights.
- New Foyer
- Expected completion date is August.
- Interior work to be completed by the Church Body.
- Stage area:
- Electrical and sound feeds need to be finished off.
- Electric run for ceiling.
- Begin the build of the Canopy above the Stage.
- Mud and paint.
- Storage Room:
- Complete Firewall.
- Build ramp and landing.
- Order fire door for stage.
- Soffit:
- Frame in.
- Ceiling:
- Work on supports for the Speaker moves.
- Doors:
- Order the New Doors that are needed.