Building Project Updates
We are currently in the process of adding onto and renovating our building!
Please pardon our mess!

GBC Building Update - 10/21/25

 New Foyer Work to be Completed

Wiring for Lighting — GBC
  • Recessed lights (84)
  • Chandeliers (4)
  • Exterior Lighting (9)

Insulation —
  • Wall insulation (GBC) — 80% complete
  • Ceiling — Contractor providing estimate

Gutters — Contractor — 10/30

Breaker Box install — GBC - by 10/31
  • Rough inspection

Drywall delivery — H.B.M. - 10/24
Drywall install — date TBD
Mudding/Sanding —(Contractor, Rickie) date TBD
Painting — in-house GBC - date TBD
Emergency lights/signs — GBC date TBD
Foyer doors installed — GBC — arrival 12/1
Trim work — GBC date TBD
Grind down concrete floor in foyer (polished floor) GBC date TBD

Completed:
  • Chair cleaning
  • Concrete around porch (foyer)
  • Water drains — gutters
  • Blacktop binder — north side

Remaining Work in Worship Center - All Dates TBD
  • New door installs 
  • Kitchen / storage room / stage door (fire) / youth door
  • Double Door (east entrance from hallway to worship center)
  • Ceiling fan installs (2)
  • Install soffit outlets
  • Baseboard trim install
  • Sound booth install
  • Exit lights install
  • Smoke detectors & horns install
  • Run conduit and wire for choir mics
  • Install shrouds around lights 
  • Look into installing spotlights for stage area
  • Paint pulpit
  • Repair floor area near stage stairs

Previously Completed

  • Canopy above the stage completed.
  • New stage mostly completed.
  • Trusses and roof added to new foyer.
  • Overhead lights installed in stage ceiling.
  • Stage drywall completed.
  • Construction on new foyer begun.
  • Plywood added to stage.
  • Siding and brick removed from north exterior wall.
  • New lights installed and diffusers added.
  • Sound boards mostly complete (waiting to move temporary stage).
  • Pillars mostly completed (waiting to move temporary stage).
  • Wall & ceiling painting completed.
  • Stage cavity opened up.
  • Ceiling painted.
  • Walls painted.
  • Drywall completed.
  • New stage started.
  • Drywall started in Worship Center.
  • Gym bathrooms completed.
  • New downspout and wider gutters installed on south side.
  • Parking lot paved and striped.
  • Storm sewer line and catch basins installed by the town.
  • Fire doors installed between Worship Center and Gym.
  • Siding and stone accents added to south side bump-out.
  • Air conditioning units for Worship Center installed.
  • Northeast corner door on Gym replaced.
  • Floor, roof, and walls constructed for south side bump-out.
  • Steel beam for south side bump-out is installed.
  • Foyer doors were replaced in March.
  • The Gym is in good shape.  
    • Bathrooms and walk-through hallway remain to be completed.
  • The trees have been removed on the north side. Tree stumps to be moved from property.  Parking lot drain area completed and available for use.  
  • Parking lot black topping being investigated to be included in 2025.
  • Phase 2 North Bump-out drawings are in process.
  • Phase 2 Target Start:  2025