Building Project Updates
We are currently in the process of adding onto and renovating our building!
Please pardon our mess!

Completed

Roadmap

  • Stage cavity opened up.
  • Ceiling painted.
  • Walls painted.
  • Drywall completed.
  • New stage started.
  • Drywall started in Worship Center.
  • Gym bathrooms completed.
  • New downspout and wider gutters installed on south side.
  • Parking lot paved and striped.
  • Storm sewer line and catch basins installed by the town.
  • Fire doors installed between Worship Center and Gym.
  • Siding and stone accents added to south side bump-out.
  • Air conditioning units for Worship Center installed.
  • Northeast corner door on Gym replaced.
  • Floor, roof, and walls constructed for south side bump-out.
  • Steel beam for south side bump-out is installed.
  • Foyer doors were replaced in March.
  • The Gym is in good shape.  
    • Bathrooms and walk-through hallway remain to be completed.
  • The trees have been removed on the north side. Tree stumps to be moved from property.  Parking lot drain area completed and available for use.  
  • Parking lot black topping being investigated to be included in 2025.
  • Phase 2 North Bump-out drawings are in process.
  • Phase 2 Target Start:  2025
Current Work: 
  • Finish up the Fire Wall in the Storage Area.
  • Continue working on the wiring for the Stage area and place the plywood down when electrical is completed.
  • Finish off the Wall Painting and maybe the ceiling as well (additional coats).
  • Continue to work on Sound Boards.
    • Place Nailing Blocks up
    • Build framework
    • Install Dacron and insulation
    • Build Burlap Caps Frames
  • Work on hanging new lights. Test dimming/diffusing.

Future Work:
  • Stage area:
    • Electrical and sound feeds
    • Plywood down 
    • Front 3' extension 
    • Electric run for ceiling 
    • Ceiling drywall
    • Frame in closets
    • Drywall closets 
    • Begin to build large overhang soffit

  • Storage Room:
    • Complete Firewall 
    • Build ramp and landing
    • Order fire door for stage

  •  Paint :
    • Remainder of ceiling  - Will do touch up as needed

  • Pillars:
    • Frame in

  • Soffit:
    • Frame in

  • Ceiling:
    • Work on supports for the Speaker moves

  • Doors:
    • Order the New Doors that are needed

  • North Bump Out:  
    • WORK TO BEGIN EARLY MAY
    • Remove Siding
    • Remove Brick