Building Project Updates
We are currently in the process of adding onto and renovating our building!
Please pardon our mess!

Completed

Roadmap

  • Trusses and roof added to new foyer.
  • Overhead lights installed in stage ceiling.
  • Stage drywall completed.
  • Construction on new foyer begun.
  • Plywood added to stage.
  • Siding and brick removed from north exterior wall.
  • New lights installed and diffusers added.
  • Sound boards mostly complete (waiting to move temporary stage).
  • Pillars mostly completed (waiting to move temporary stage).
  • Wall & ceiling painting completed.
  • Stage cavity opened up.
  • Ceiling painted.
  • Walls painted.
  • Drywall completed.
  • New stage started.
  • Drywall started in Worship Center.
  • Gym bathrooms completed.
  • New downspout and wider gutters installed on south side.
  • Parking lot paved and striped.
  • Storm sewer line and catch basins installed by the town.
  • Fire doors installed between Worship Center and Gym.
  • Siding and stone accents added to south side bump-out.
  • Air conditioning units for Worship Center installed.
  • Northeast corner door on Gym replaced.
  • Floor, roof, and walls constructed for south side bump-out.
  • Steel beam for south side bump-out is installed.
  • Foyer doors were replaced in March.
  • The Gym is in good shape.  
    • Bathrooms and walk-through hallway remain to be completed.
  • The trees have been removed on the north side. Tree stumps to be moved from property.  Parking lot drain area completed and available for use.  
  • Parking lot black topping being investigated to be included in 2025.
  • Phase 2 North Bump-out drawings are in process.
  • Phase 2 Target Start:  2025
Current Work: 
  • Hang additional lights.
  • New Foyer
    • Expected completion date is August. 
    • Interior work to be completed by the Church Body.
  • Stage area:
    • Electrical and sound feeds need to be finished off.
    • Electric run for ceiling.
    • Begin the build of the Canopy above the Stage.
    • Mud and paint.
  • Storage Room:
    • Complete Firewall. 
    • Build ramp and landing.
    • Order fire door for stage.
  • Soffit:
    • Frame in.
  • Ceiling:
    • Work on supports for the Speaker moves.
  • Doors:
    • Order the New Doors that are needed.