Building Project Updates
We are currently in the process of adding onto and renovating our building!
Please pardon our mess!

Recent Updates

  • New downspout and wider gutters installed on south side.
  • Parking lot paved and striped.
  • Storm sewer line and catch basins installed by the town.
  • Fire doors installed between Worship Center and Gym.
  • Siding and stone accents added to south side bump-out.
  • Air conditioning units for Worship Center installed.
  • Northeast corner door on Gym replaced.
  • Floor, roof, and walls constructed for south side bump-out.
  • Steel beam for south side bump-out is installed.
  • Foyer doors were replaced in March.
  • The Gym is in good shape.  
    • Bathrooms and walk-through hallway remain to be completed.
  • The trees have been removed on the north side. Tree stumps to be moved from property.  Parking lot drain area completed and available for use.  
  • Parking lot black topping being investigated to be included in 2025.
  • Phase 2 North Bump-out drawings are in process.
  • Phase 2 Target Start:  2025